The westbound lanes of CM Recto Avenue for the Bitan-ag Bridge Project is now nearing completion as construction of the bridge structure continues.
As shown, the approaches along the Mindanao University of Science & Technology (MUST) Campus has been completed with minor drainage works still ongoing.
You could see the full elevation of the bridge as it passes the Limketkai-MUST Overpass.
The bridge will be at level with the passing cars as shown.
Rough finishing at the bridge site is observed.
Excavation works are still ongoing at the bridge site.
Civil works still ongoing as the road descends towards Osmena junction.
Once this section is done, the eastbound lanes will then be closed to traffic. But westbound vehicles can now use the completed westbound lanes.